e|agenda.NET
Sarasota County Schools
THE SCHOOL BOARD OF SARASOTA COUNTY, FLORIDA Landings Administrative Complex 1980 Landings Blvd. 3:00 P. M.
September 16, 2008 Board Meeting
Agenda Item #31


Title
ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE WOODLAND MIDDLE SCHOOL - PHASE 2: VERTICAL CONSTRUCTION PROJECT

Description
The architect has prepared the Certificate of Substantial Completion and the final punch list.  The project is substantially complete in accordance with the contract documents.  A copy of the final punch list is available for review at the Construction Services Department.

Recommendation
That the work performed by Kraft Construction Company, Inc. for the Woodland Middle School - Phase 2: Vertical Construction project be accepted as substantially complete as of 6/30/2008.

Contact
LEMPE & COLLINS

Financial Impact
N/A


Attachment:  BAIenc9-16-08WoodlandPh2VertConstSC.pdf